Basic calculation mode for processes (process reference)
The Basic calculation with reference to a process calculates process times, manufacturing times and setup times. Hence, unit-related manufacturing costs and setup costs are calculated.
- Select the element in the project structure you wish to assign Basic mode to.
- In the ribbon, click on Start > Set Mode ("Edit" group)
> Basic
. - In the "Manufacturing" group, enter the time required by the manufacturing for the process in the "Time" entry field, and the incurred cost rate in the "Cost rate" entry field.
- In the "Setup" group, enter the time required by the setup for the process in the "Time" entry field, and the incurred cost rate in the "Cost rate" entry field.
- Click OK.
The Basic dialog opens.